15 signed an agreement for design and construction of a high-voltage direct current (HVDC) back-to-back converter station with a 400 kV switchyard in Alytus, reports ELTA. The value of the contract is 288 million litas (83.4 million euros).
The preliminary value of the LitPol Link project being implemented by Lithuania and Poland is 1.28 billion litas.

The HVDC back-to-back converter station that is the key element in the LitPol Link interconnection will be built next to the Alytus transformer substation. Construction work will begin in spring 2014 and will be completed by December 2015. A high-voltage electricity transmission line will…